Moshannon-Milesburg substation interconnection queue

1 active project totalling 50 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
50active MW
2total filed
Queue IDProjectkVMWResourceStatus
AE2-262 MPG Solar 230 50 Solar Engineering and Procurement
AA1-085 Centre County Wind Facility 230 10.7 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.