Givens-Mechanicsburg substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 3 with terminal status (shown grayed).
3 PJM queue filings name Givens-Mechanicsburg as the point of interconnection, all in Champaign County, OH.
Target commercial operation date as filed: Sep 2029 (3 filings).
0active projects
0active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AE2-305 | Hillclimber Solar | 138 | 46.8 | Solar | Withdrawn | Sep 2029 |
| AF1-054 | Hillclimber Solar | 138 | 23.1 | Solar | Withdrawn | Sep 2029 |
| AF1-053 | Hillclimber Solar | 138 | 16 | Battery | Withdrawn | Sep 2029 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Same name on other Substation Scout pages
Other sources that print a substation named “Givens-Mechanicsburg” in OH. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each.
- Givens - Mechanicsburg: PJM interconnection queue (OH)
Other PJM queue substations in Champaign County, OH
- East Lima-Marysville: 3 active, 89.5 MW of 6 filed
- East Sidney-Quincy: 3 active, 86.4 MW of 5 filed
- Kings Creek: none active of 6 filed
- Mechanicsburg - Darby: none active of 3 filed
- West Mingo: none active of 3 filed
- Woodstock: none active of 3 filed
- Givens - Mechanicsburg: none active of 2 filed
- Mechanicsburg: none active of 2 filed