Edison-Gravel Pit substation interconnection queue
1 active project totaling 90 MW in the PJM queue, plus 1 with terminal status (shown grayed).
2 PJM queue filings name Edison-Gravel Pit as the point of interconnection, all in St. Joseph County, IN.
Target commercial operation dates as filed run from Jan 2025 to Dec 2025 (2 filings).
1active projects
90active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AF1-158 | Honeysuckle Solar Project | 138 | 90 | Solar | In Service | Jan 2025 |
| AI2-291 | Edison-Gravel Pit 138 kV | 138 | 10.5 | Solar | Withdrawn | Dec 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in St. Joseph County, IN
- Dumont-Olive: 2 active, 715 MW of 2 filed
- Dumont: 3 active, 320 MW of 7 filed
- Olive: 1 active, 2.5 MW of 2 filed
- Dumont-Stillwell: none active of 3 filed
- Elderberry-Dumont: none active of 2 filed
- New Carlisle: none active of 2 filed
- Olive - Dumont: none active of 2 filed
- Olive-Dumont: none active of 2 filed
Site Scanner