Honeysuckle Solar Project (AF1-158) is listed in the PJM interconnection queue as a 90 MW solar project in St. Joseph County, IN. The filing names Edison-Gravel Pit as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of January 31, 2025.
| Queue ID | AF1-158 |
|---|---|
| Project name | Honeysuckle Solar Project |
| Status (as published) | In Service |
| Substation | Edison-Gravel Pit |
| Point of interconnection | Edison-Gravel Pit 138 kV |
| County | St. Joseph |
| State | IN |
| Voltage | 138 kV |
| Capacity | 90 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2025-01-31 |
| Source dataset | serial |
Same substation and county
Edison-Gravel Pit substation: 2 requests in the PJM queue, 1 active totaling 90 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AI2-291 | Edison-Gravel Pit 138 kV | 10.5 | Solar | Withdrawn |
St. Joseph, IN: 33 requests in the PJM queue, 11 active totaling 1,388.3 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 150 |
| MW capacity | 90 |
| MFO | 150 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.