Dumont-Stillwell substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 3 with terminal status (shown grayed).

3 PJM queue filings name Dumont-Stillwell as the point of interconnection, all in St. Joseph County, IN.

Target commercial operation dates as filed run from Jun 2020 to Jun 2023 (2 filings).

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AD2-080 Dumont-Stillwell 345kV 345 309 Not reported Withdrawn Jun 2020
AD2-054 Dumont-Stillwell 345kV 345 50 Not reported Withdrawn n/r
AF2-320 Dumont-Stillwell 345 kV 345 48 Not reported Withdrawn Jun 2023

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in St. Joseph County, IN

All 33 PJM queue filings in St. Joseph County, IN.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first