Substation Scout

Catoctin substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 5 with terminal status (shown greyed).

0active projects
0active MW
5total filed
Queue IDProjectkVMWResourceStatus
AB2-181 Catoctin 138kV 138 14 Solar Withdrawn
AA2-145 Hessong Birdge Solar Facility 34.5 10.9 Solar Withdrawn
AA2-146 Catoctin 34.5kV 34.5 10.9 Solar Withdrawn
AC1-039 Catoctin Furnace Solar Facility 34 10.4 Solar Withdrawn
AA2-143 Catoctin 12.5kV 12.5 2.7 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.