Wayne, IN interconnection queue
1 active project totalling 200 MW in the PJM queue, plus 4 with terminal status (shown greyed).
1active projects
200active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-1404 | Desoto - Tanners Creek 345 kV | 345 | 200 | Battery | Active |
| C01-1202 | Desoto - Tanners Creek 345 kV | 345 | 184 | Solar | Withdrawn |
| AI1-085 | Tanners Creek - DeSoto 345 kV | 345 | 174 | Solar | Withdrawn |
| AG2-170 | Whitewater Valley Power Station 69 kV | 69 | 58.7 | Solar | Withdrawn |
| AI1-140 | Selma Parker - Richmond 138 kV | 138 | 40 | Hybrid | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.