Cooper substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 5 with terminal status (shown greyed).

0active projects
0active MW
5total filed
Queue IDProjectkVMWResourceStatus
W1-010 Cooper n/r 7.6 Solar Withdrawn
Y1-022 Cooper n/r 3.8 Solar Withdrawn
AF2-131 Cooper 34.5 kV 34.5 3 Solar Withdrawn
AH2-321 Cooper 34.5 kV 34.5 3 Solar Withdrawn
AH1-139 Cooper 34.5kV 34.5 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.