Clark Summit-Emlenton substation interconnection queue
1 active project totaling 11.3 MW in the PJM queue, plus 2 with terminal status (shown grayed).
3 PJM queue filings name Clark Summit-Emlenton as the point of interconnection, all in Venango County, PA.
Target commercial operation dates as filed run from Sep 2022 to Jul 2025 (3 filings).
1active projects
11.3active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AF2-165 | Cardinal Solar | 34.5 | 11.3 | Solar | In Service | Jul 2025 |
| AI2-058 | Clark Summit-Emlenton 34.5 kV | 34.5 | 7.3 | Solar | Withdrawn | Jan 2025 |
| AG1-139 | Clark Summit-Emlenton 34.5 kV | 34.5 | 4.8 | Solar | Withdrawn | Sep 2022 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Venango County, PA
- Handsome Lake: 1 active, 466 MW of 2 filed
- Utica Junction: 1 active, 110 MW of 2 filed
- Emlenton: 1 active, 18 MW of 4 filed
- McConnellsburg-Guilford: none active of 5 filed
- Grandview: none active of 3 filed
- Titusville: none active of 3 filed
- Venango: none active of 2 filed