Branchville-Holiday Lakes substation interconnection queue
1 active project totaling 0 MW in the PJM queue, plus 3 with terminal status (shown grayed).
4 PJM queue filings name Branchville-Holiday Lakes as the point of interconnection, all in Sussex County, NJ.
Target commercial operation dates as filed run from Feb 2012 to Jan 2025 (4 filings).
1active projects
0active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| W3-126 | Syncarpha Ty Solar Farm | 34.5 | 6.4 | Solar | Withdrawn | Sep 2014 |
| X1-105 | Branchville-Holiday Lakes 34.5kV | 34.5 | 4.3 | Solar | Withdrawn | Feb 2012 |
| W2-084 | Roberts Solar Farm | 34.5 | 3.8 | Solar | Withdrawn | Jun 2014 |
| AF1-019 | Viridity Energy Solutions Montague Storage | 34.5 | 0 | Battery | In Service | Jan 2025 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Sussex County, NJ
- Sussex: 2 active, 6.6 MW of 11 filed
- Branchville-Sussex: 1 active, 3.8 MW of 4 filed
- Vernon: none active of 4 filed
- Andover: none active of 3 filed
- Andover-Kittatinny: none active of 3 filed
- Wantage: none active of 3 filed
- Kittatinny-Newton: 1 active, 0 MW of 2 filed
- Lafayette: none active of 2 filed
- Sparta-Woodruff's Gap: 1 active, 0 MW of 2 filed