Bluff Point substation interconnection queue

3 active projects totaling 147.2 MW in the PJM queue, plus 4 with terminal status (shown grayed).

Target commercial operation dates as filed run from Dec 2011 to Dec 2030 (7 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: AEP (1 filing).

3active projects
147.2active MW
7total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1755 Bluff Point 138 kV 138 120 Battery Active Dec 2030
AH2-227 Bluff Point 138 kV 138 75 Battery Withdrawn Dec 2026
AH2-223 Bluff Point 138 kV 138 30 Solar Withdrawn Dec 2025
S71 Bluff Point 138 24 Wind In Service Dec 2017
W2-068 Bluff Point 138kV 138 19.5 Wind Withdrawn Dec 2011
Y3-024 Wabash Valley Power Association, Inc. 12 3.2 Gas In Service Jun 2015
AA2-106 Bluff Point 69kV 69 0 Battery Withdrawn Dec 2018

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Bluff Point (AEP, 1 mention).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Other PJM queue substations in Jay County, IN

All 30 PJM queue filings in Jay County, IN.

Other PJM queue substations in Mercer County, OH

No other substation in Mercer County, OH is named as a point of interconnection in the PJM queue.

All 3 PJM queue filings in Mercer County, OH.