Substation Scout

Jay, IN interconnection queue

10 active projects totalling 477.4 MW in the PJM queue, plus 20 with terminal status (shown greyed).

10active projects
477.4active MW
30total filed
Queue IDProjectkVMWResourceStatus
C01-1755 Bluff Point 138 kV 138 120 Battery Active
AE1-189 Penville-Adams 138 kV 138 103 Solar Withdrawn
AI1-081 Jay - DeSoto 138 kV 138 100 Hybrid Withdrawn
AH2-114 Not reported n/r 96.6 Solar Withdrawn
AE2-089 Skycrest Solar Energy Center 138 93 Solar Suspended
AF1-223 Blackford Solar Energy Project 345 90 Solar Under Construction
AF2-212 Shelby 138 kV 138 90 Solar Withdrawn
AH1-041 Pennville 138 kV 138 75 Solar Withdrawn
AH2-227 Bluff Point 138 kV 138 75 Battery Withdrawn
AG1-006 Jay 138 kV 138 60 Solar Withdrawn
AG1-047 Sun Chief Solar Farm 138 60 Solar Engineering and Procurement
AH1-308 Pennville - Adams 138 kV 138 50 Battery Withdrawn
AH1-431 Pennville 138 kV 138 50 Battery Withdrawn
AH2-371 Jay 138 kV 138 50 Battery Withdrawn
AI2-172 Pennville - Adams 138 kV 138 37.2 Solar Withdrawn
C01-1636 Pennville - Adams 138 kV 138 37.2 Solar Active
AI2-399 Jay 138 kV 138 36 Solar Withdrawn
C01-1593 Jay 138 kV 138 30.8 Wind Active
AG2-577 Jay 138 kV 138 30 Solar Withdrawn
AG2-578 Jay 69 kV 69 30 Solar Withdrawn
AH2-223 Bluff Point 138 kV 138 30 Solar Withdrawn
AG1-324 New Jay PV & BESS 138 27.9 Hybrid Pending Termination
S71 Bluff Point 138 24 Wind In Service
AC2-176 Bitter Ridge Wind Farm 138 16.9 Wind In Service
S26 Bluff Point-Jay 138kV 138 15 Wind Withdrawn
AI2-422 Jay 138 kV 138 12 Solar Withdrawn
AI2-423 Jay 69 kV 69 12 Solar Withdrawn
Y3-024 Wabash Valley Power Association, Inc. 12 3.2 Gas In Service
AG1-017 Bitter Ridge Wind Farm 138 2.3 Wind In Service
AA2-106 Bluff Point 69kV 69 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.