Beaver substation interconnection queue
6 active projects totalling 1,310 MW in the PJM queue, plus 1 with terminal status (shown greyed).
6active projects
1,310active MW
7total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-2183 | Beaver 138 kV | 138 | 700 | Gas | Active |
| AG1-500 | West Lorain Power Plant 345 kV | 345 | 385.5 | Gas | Engineering and Procurement |
| C01-2182 | Beaver 138 kV | 138 | 173.5 | Gas | Active |
| AC1-150 | Beaver 138kV | 138 | 76 | Solar | Withdrawn |
| AF2-004 | West Lorain Power Plant 345 kV | 345 | 33 | Gas | Engineering and Procurement |
| AG1-501 | West Lorain 138 kV Power Plant | 138 | 10 | Gas | Engineering and Procurement |
| AF2-005 | West Lorain 138 kV Power Plant | 138 | 8 | Gas | Engineering and Procurement |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.