Otter Creek Wind Farm (AA1-018) is listed in the PJM interconnection queue as a 19.5 MW wind project in Livingston County, IL. The filing names Powerton-Goodings Grove as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of January 17, 2020.

Queue IDAA1-018
Project nameOtter Creek Wind Farm
Status (as published)In Service
SubstationPowerton-Goodings Grove
Point of interconnectionPowerton-Goodings Grove
CountyLivingston
StateIL
VoltageNot reported
Capacity19.5 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2020-01-17
Source datasetserial

Same substation and county

Powerton-Goodings Grove substation: 4 requests in the PJM queue, 2 active totaling 79.5 MW.

Queue IDProjectMWResourceStatus
O22Top Crop Generating Facility60WindIn Service
O27Powerton-Goodings Grove 345kV60GasWithdrawn
W2-046Powerton-Goodings Grove 345kV58.5WindWithdrawn

Livingston, IL: 47 requests in the PJM queue, 13 active totaling 1,544.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy150
MW capacity19.5
MFO150

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first