Otter Creek Wind Farm
PJM queue ID AA1-018
Otter Creek Wind Farm (AA1-018) is listed in the PJM interconnection queue as a 19.5 MW wind project in Livingston County, IL. The filing names Powerton-Goodings Grove as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of January 17, 2020.
| Queue ID | AA1-018 |
|---|---|
| Project name | Otter Creek Wind Farm |
| Status (as published) | In Service |
| Substation | Powerton-Goodings Grove |
| Point of interconnection | Powerton-Goodings Grove |
| County | Livingston |
| State | IL |
| Voltage | Not reported |
| Capacity | 19.5 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2020-01-17 |
| Source dataset | serial |
Same substation and county
Powerton-Goodings Grove substation: 4 requests in the PJM queue, 2 active totaling 79.5 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| O22 | Top Crop Generating Facility | 60 | Wind | In Service |
| O27 | Powerton-Goodings Grove 345kV | 60 | Gas | Withdrawn |
| W2-046 | Powerton-Goodings Grove 345kV | 58.5 | Wind | Withdrawn |
Livingston, IL: 47 requests in the PJM queue, 13 active totaling 1,544.4 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 150 |
| MW capacity | 19.5 |
| MFO | 150 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.