Substation Scout

Dresden - Ponitac Midpoint 345 kV

PJM queue ID C01-1098

Dresden - Ponitac Midpoint 345 kV (C01-1098) is listed in the PJM interconnection queue as a 185 MW hybrid project in Livingston County, IL. The filing names Dresden - Ponitac Midpoint as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of September 14, 2029.

Queue IDC01-1098
Project nameDresden - Ponitac Midpoint 345 kV
Status (as published)Active
SubstationDresden - Ponitac Midpoint
Point of interconnectionDresden - Ponitac Midpoint 345 kV
CountyLivingston
StateIL
Voltage345 kV
Capacity185 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalized for filtering)
Target commercial operation2029-09-14
Source datasetcycle

Same substation and county

Livingston, IL: 47 requests in the PJM queue, 13 active totaling 1,544.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperCPV Prairie Dock Solar, LLC
Transmission ownerComEd
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy185.0
MW capacity185.0
MFO185.0
Submitted date4/27/2026
Last updated6/18/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first