Tap Angstrom - Grissom substation interconnection queue
4 active projects totaling 1,044.3 MW in the ERCOT queue.
4 ERCOT queue filings name Tap Angstrom - Grissom as the point of interconnection, all in San Patricio County, TX.
Target commercial operation dates as filed run from Oct 2028 to Dec 2029 (4 filings). 4 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Vaquero Solar, LLC (1 filing), Gulf Gateway Solar, LLC (1 filing), Gulf Gateway Storage, LLC (1 filing), Diamond B Storage, LLC (1 filing).
4active projects
1,044.3active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 26INR0211 | Titus Low Carbon Ventures Solar 1 | 345 | 338 | Solar | SS Completed, FIS Started, IA | Oct 2028 |
| 27INR0492 | Gulf Gateway Solar One | 345 | 301.4 | Solar | SS Completed, FIS Started, No IA | Dec 2029 |
| 27INR0556 | Gulf Gateway Storage One | 345 | 301.4 | Battery | SS Completed, FIS Started, No IA | Dec 2029 |
| 26INR0428 | Diamond Cowboy Storage | 345 | 103.5 | Battery | SS Completed, FIS Started, IA | Oct 2028 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in San Patricio County, TX
- Goddard: 3 active, 677.7 MW of 3 filed
- Tap Angstrom – Naismith: 2 active, 565.1 MW of 2 filed
- KATOEN (Bus#): 2 active, 557.9 MW of 2 filed
- Tap Grissom – Lon C Hill: 2 active, 447.5 MW of 2 filed
- Bus # Haisley 4A: 2 active, 207.9 MW of 2 filed
Site Scanner