Substation Scout

Gulf Gateway Solar One

ERCOT queue ID 27INR0492

Queue ID27INR0492
Project nameGulf Gateway Solar One
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Angstrom - Grissom
Point of interconnectionTap 345 kV 8249 Angstrom - 8624 Grissom
CountySan Patricio
StateTX
Voltage345 kV
Capacity301.4 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-12-01
Source datasetlarge

Additional filed fields

Interconnecting EntityGulf Gateway Solar, LLC
Cdr ZoneCOASTAL
Fuel CodeSOL
Technology CodePV
Screening Study Complete45857
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.