Goddard substation interconnection queue

3 active projects totalling 676.3 MW in the ERCOT queue.

3active projects
676.3active MW
3total filed
Queue IDProjectkVMWResourceStatus
29INR0227 San Patricio Energy Center BESS 345 300.8 Battery SS Completed, FIS Started, No IA
28INR0223 Bayou Creek Solar 345 255.5 Solar SS Completed, FIS Started, IA
22INR0392 Kalina Solar 345 120 Solar SS Completed, FIS Started, No IA