Tap Grissom – Lon C Hill substation interconnection queue

2 active projects totaling 447.5 MW in the ERCOT queue.

2 ERCOT queue filings name Tap Grissom – Lon C Hill as the point of interconnection, all in San Patricio County, TX.

Target commercial operation date as filed: Jul 2029 (2 filings). 2 active filings target a date after November 27, 2026.

Interconnecting entity as filed: RWE Clean Energy Development, LLC (2 filings).

2active projects
447.5active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
27INR0132 Palo Verde Wind 345 297.5 Wind SS Completed, FIS Started, IA Jul 2029
27INR0227 PALO VERDE BESS 345 150 Battery SS Completed, FIS Started, No IA Jul 2029

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Other ERCOT queue substations in San Patricio County, TX

All 28 ERCOT queue filings in San Patricio County, TX.