Diamond Cowboy Storage
ERCOT queue ID 26INR0428
Diamond Cowboy Storage (26INR0428) is listed in the ERCOT interconnection queue as a 103.5 MW battery project in San Patricio County, TX. The filing names Tap Angstrom - Grissom as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of October 16, 2028. It records the screening study as complete on July 12, 2024 and the interconnection agreement as signed on May 26, 2026.
| Queue ID | 26INR0428 |
|---|---|
| Project name | Diamond Cowboy Storage |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Tap Angstrom - Grissom |
| Point of interconnection | Tap 345kV 8249 Angstrom - 8624 Grissom |
| County | San Patricio |
| State | TX |
| Voltage | 345 kV |
| Capacity | 103.5 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-10-16 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Tap Angstrom - Grissom substation: 4 requests in the ERCOT queue, 4 active totaling 1,044.3 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 26INR0211 | Titus Low Carbon Ventures Solar 1 | 338 | Solar | SS Completed, FIS Started, IA |
| 27INR0492 | Gulf Gateway Solar One | 301.4 | Solar | SS Completed, FIS Started, No IA |
| 27INR0556 | Gulf Gateway Storage One | 301.4 | Battery | SS Completed, FIS Started, No IA |
San Patricio, TX: 28 requests in the ERCOT queue, 27 active totaling 6,857.5 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Diamond B Storage, LLC |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2026-05-26 |
| Screening study complete | 2024-07-12 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.