Bus # Haisley 4A substation interconnection queue
2 active projects totaling 207.9 MW in the ERCOT queue.
2 ERCOT queue filings name Bus # Haisley 4A as the point of interconnection, all in San Patricio County, TX.
Target commercial operation date as filed: Jul 2029 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Vaquero II Solar LLC (1 filing), Vaquero II Storage LLC (1 filing).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 28INR0305 | Iron Cowboy Solar | 138 | 144.6 | Solar | SS Completed, FIS Started, IA | Jul 2029 |
| 28INR0306 | Iron Cowboy Storage | 138 | 63.3 | Battery | SS Completed, FIS Started, IA | Jul 2029 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Tracked changes at this substation
2 changes to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-09-07 | 28INR0305 | Status change | n/a | SS Completed, FIS Started, No IA → SS Completed, FIS Started, IA |
| 2026-09-07 | 28INR0306 | Status change | n/a | SS Completed, FIS Started, No IA → SS Completed, FIS Started, IA |
Other ERCOT queue substations in San Patricio County, TX
- Tap Angstrom - Grissom: 4 active, 1,044.3 MW of 4 filed
- Goddard: 3 active, 677.7 MW of 3 filed
- Tap Angstrom – Naismith: 2 active, 565.1 MW of 2 filed
- KATOEN (Bus#): 2 active, 557.9 MW of 2 filed
- Tap Grissom – Lon C Hill: 2 active, 447.5 MW of 2 filed