TEXPO

ERCOT queue ID 22INR0497

Queue ID22INR0497
Project nameTEXPO
Status (as published)SS Completed, FIS Started, No IA
SubstationRiley
Point of interconnection6101 Riley 345 kV
CountyWilbarger
StateTX
Voltage345 kV
Capacity680 MW
Resource (as published)GAS/ST
Resource categoryGas (normalised for filtering)
Target commercial operation2027-10-31
Source datasetlarge

Additional filed fields

Interconnecting EntityOklaunion Power Station, LLC
Cdr ZoneWEST
Fuel CodeGAS
Technology CodeST
Screening Study Complete44344
Air PermitNot Required
Water Availability44683

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.