Revolution substation interconnection queue

3 active projects totaling 451.6 MW in the ERCOT queue.

3 ERCOT queue filings name Revolution as the point of interconnection, all in Navarro County, TX.

Target commercial operation dates as filed run from Feb 2027 to Sep 2029 (3 filings). 3 active filings target a date after November 27, 2026.

Interconnecting entity as filed: Armadillo Solar Center, LLC (2 filings), Main Horn Solar LLC (1 filing).

3active projects
451.6active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
27INR0614 Armadillo Solar Phase 2 138 200.7 Solar SS Completed, FIS Started, No IA Mar 2027
21INR0421 Armadillo Solar 138 150.5 Solar SS Completed, FIS Completed, IA Feb 2027
28INR0467 Main Horn Solar 138 100.4 Solar SS Completed, FIS Started, No IA Sep 2029

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Other ERCOT queue substations in Navarro County, TX

All 29 ERCOT queue filings in Navarro County, TX.