Armadillo Solar (21INR0421) is listed in the ERCOT interconnection queue as a 150.5 MW solar project in Navarro County, TX. The filing names Revolution as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of February 1, 2027. It records the screening study as complete on November 22, 2019, the full interconnection study as approved on October 8, 2025 and the interconnection agreement as signed on February 2, 2021.

Queue ID21INR0421
Project nameArmadillo Solar
Status (as published)SS Completed, FIS Completed, IA
SubstationRevolution
Point of interconnection3387 Revolution 138kV
CountyNavarro
StateTX
Voltage138 kV
Capacity150.5 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2027-02-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Revolution substation: 3 requests in the ERCOT queue, 3 active totaling 451.6 MW.

Queue IDProjectMWResourceStatus
27INR0614Armadillo Solar Phase 2200.7SolarSS Completed, FIS Started, No IA
28INR0467Main Horn Solar100.4SolarSS Completed, FIS Started, No IA

Navarro, TX: 29 requests in the ERCOT queue, 26 active totaling 4,412.7 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityArmadillo Solar Center, LLC
CDR reporting zoneNORTH
Fuel codeSOL
Technology codePV
Interconnection agreement signed2021-02-02
Screening study complete2019-11-22
Full interconnection study approved2025-10-08
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first