Armadillo Solar
ERCOT queue ID 21INR0421
Armadillo Solar (21INR0421) is listed in the ERCOT interconnection queue as a 150.5 MW solar project in Navarro County, TX. The filing names Revolution as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of February 1, 2027. It records the screening study as complete on November 22, 2019, the full interconnection study as approved on October 8, 2025 and the interconnection agreement as signed on February 2, 2021.
| Queue ID | 21INR0421 |
|---|---|
| Project name | Armadillo Solar |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Revolution |
| Point of interconnection | 3387 Revolution 138kV |
| County | Navarro |
| State | TX |
| Voltage | 138 kV |
| Capacity | 150.5 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-02-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Revolution substation: 3 requests in the ERCOT queue, 3 active totaling 451.6 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 27INR0614 | Armadillo Solar Phase 2 | 200.7 | Solar | SS Completed, FIS Started, No IA |
| 28INR0467 | Main Horn Solar | 100.4 | Solar | SS Completed, FIS Started, No IA |
Navarro, TX: 29 requests in the ERCOT queue, 26 active totaling 4,412.7 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Armadillo Solar Center, LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2021-02-02 |
| Screening study complete | 2019-11-22 |
| Full interconnection study approved | 2025-10-08 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.