Tap BRIAR_CRK_8 – POWELL1_8 substation interconnection queue
2 active projects totaling 125.8 MW in the ERCOT queue.
2 ERCOT queue filings name Tap BRIAR_CRK_8 – POWELL1_8 as the point of interconnection, all in Navarro County, TX.
Target commercial operation date as filed: Nov 2027 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Orca Falls Solar, LLC (2 filings).
2active projects
125.8active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 26INR0130 | Elm Flats Solar SLF | 138 | 125.8 | Solar | SS Completed, FIS Started, IA | Nov 2027 |
| 26INR0131 | Elm Flats Storage SLF | 138 | 0 | Battery | SS Completed, FIS Started, IA | Nov 2027 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Navarro County, TX
- Tap Venus - Navarro: 2 active, 663.6 MW of 2 filed
- tap Venus - Navarro: 2 active, 555 MW of 2 filed
- Revolution: 3 active, 451.6 MW of 3 filed
- Tap # Big Onion - # Navarro: 2 active, 304.5 MW of 2 filed
- Tap Navarro - Limestone: 2 active, 203.3 MW of 2 filed
- Tap Kopprl Capacitor Yard - Navarro: 2 active, 126.8 MW of 2 filed
- Haney (213) - Hubbard_8 Line: 1 active, 81.6 MW of 2 filed