Substation Scout

Tap # Big Onion - # Navarro substation interconnection queue

2 active projects totalling 304.5 MW in the ERCOT queue.

2active projects
304.5active MW
2total filed
Queue IDProjectkVMWResourceStatus
24INR0206 Glasgow Solar 345 203.5 Solar SS Completed, FIS Started, IA
24INR0207 Glasgow Storage 345 101 Battery SS Completed, FIS Started, IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.