ERCOT queue ID 22INR0392

Kalina Solar (22INR0392) is listed in the ERCOT interconnection queue as a 120 MW solar project in San Patricio County, TX. The filing names Goddard as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of May 31, 2029. It records the screening study as complete on October 28, 2020.

Queue ID22INR0392
Project nameKalina Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationGoddard
Point of interconnection8606 Goddard 345kV
CountySan Patricio
StateTX
Voltage345 kV
Capacity120 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2029-05-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Goddard substation: 3 requests in the ERCOT queue, 3 active totaling 677.7 MW.

Queue IDProjectMWResourceStatus
29INR0227San Patricio Energy Center BESS300.8BatterySS Completed, FIS Started, No IA
28INR0223Bayou Creek Solar256.9SolarSS Completed, FIS Started, IA

San Patricio, TX: 28 requests in the ERCOT queue, 27 active totaling 6,857.5 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityAurora Solar LLC
CDR reporting zoneCOASTAL
Fuel codeSOL
Technology codePV
Screening study complete2020-10-28
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first