1 active project totalling 204 MW in the BPA queue, plus 2 with terminal status (shown greyed).

1active projects
204active MW
3total filed
Queue IDProjectkVMWResourceStatus
G0389 Not reported 500 207 Wind WITHDRAWN
G0390 Not reported 500 207 Wind WITHDRAWN
G0362 Wheatridge East Substation 500 204 Wind ENERGIZED

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.