Batavia Rd.

Named in 1 PJM planning document for 1 project, on December 5, 2023.

Newdescribed as
BGEzone
230 kVkV as printed
1mentions

Described as new. The quoted wording calls this substation new. “Build new Batavia Rd. 230 kV switching station” — source, page 20

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

Part of a named transmission project: Brandon Shores deactivation upgrades ($1,513.96 million).

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
PJM recommended adjustments to Earlier Approved Brandon Shores De-Activation Scope
B3780
Not printed $60M 2026-2028 Not printed 2023-12-05
TEAC

Other substations in this project

“PJM recommended adjustments to Earlier Approved Brandon Shores De-Activation Scope” also names 13 other substations, with what the most recent document says about each.

Every mention

DateDocumentProjectWhat the document says about it
2023-12-05 TEAC
Item 15 - Reliability Analysis Update 2022 Window 3 p. 20
PJM recommended adjustments to Earlier Approved Brandon Shores De-Activation Scope “Build new Batavia Rd. 230 kV switching station”
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.