Substation Scout

Elk Grove East

Named in 3 PJM planning documents for 2 projects, from September 19, 2025 to October 8, 2025.

Existingdescribed as
COMEDzone
138 kV, 138kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Customer in Elk Grove
ComEd-2024-003 · s3584.1; s3584.2
Engineering $319.4M 12/31/2027 (s3584.1), 12/31/2028 (s3584.2) 250 MW 2025-09-19
SRRTEP Western
Customer in Elk Grove
ComEd-2024-004 · s3583.1, s3583.2
Engineering $40.6M 12/31/2026 (s3583.1), 12/31/2027 (s3583.2) 260 MW 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate $319.4M → $289.4M 2025-09-19 2025-10-08
Status engineering (Engineering) → conceptual (Conceptual) 2025-09-19 2025-10-08
Substations named COMED DIERKING; COMED ELK GROVE EAST; COMED ITASCA; COMED PINE → DIERKING; ELK GROVE EAST; ITASCA; PINE 2025-10-08 Not reported
Cost estimate $14.31 M → $40.6M 2024-12-03 2025-10-08
In-service date 6/1/2029 → 12/31/2026 (s3583.1), 12/31/2027 (s3583.2) 2024-12-03 2025-10-08
Substations named BUSSE; DES PLAINES; ITASCA → ELK GROVE EAST; ITASCA 2024-12-03 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
ComEd local plan submission of the supplemental projects for 2025 RTEP p. 14
Customer in Elk Grove “Install 4 new 138kV GIS CBs to the breaker-and-a-half configuration at Elk Grove East”
138 kV
2026-09-08* SRRTEP Western
ComEd local plan submission of the supplemental projects for 2025 RTEP p. 17
Customer in Elk Grove “underground lines from ComEd Elk Grove East substation”
138kV
2025-10-08 TEAC
Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2025 p. 14
Customer in Elk Grove “Install 4 new 138kV GIS CBs to the breaker-and-a-half configuration at Elk Grove East”
138kV
2025-09-19 SRRTEP Western
Item 04 - ComEd Supplemental Projects p. 8
Customer in Elk Grove “lines from ComEd Elk Grove East substation”
138kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this