Williams substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 3 with terminal status (shown greyed).

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatus
AI2-354 Williams 138 kV 138 58.7 Wind Withdrawn
AA1-062 Mt. Storm Wind Force 138 22.1 Wind Withdrawn
AE1-003 Williams 138 kV 138 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.