Waugh Chapel substation interconnection queue
1 active project totalling 490 MW in the PJM queue, plus 4 with terminal status (shown greyed).
1active projects
490active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-2159 | Waugh Chapel 230 kV | 230 | 490 | Battery | Active |
| AG1-104 | Chapel Energy Storage Facility | 230 | 120 | Battery | Withdrawn |
| C01-1862 | Waugh Chapel 115kV 115 kV | 115 | 42.8 | Solar | Withdrawn |
| AF2-435 | Waugh Chapel 115 kV | 115 | 33 | Solar | Withdrawn |
| AG2-617 | Waugh Chapel 115 kV | 115 | 33 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.