Brandon Shores substation interconnection queue

2 active projects totaling 410.4 MW in the PJM queue, plus 3 with terminal status (shown grayed).

5 PJM queue filings name Brandon Shores as the point of interconnection, all in MD.

Target commercial operation dates as filed run from Jul 2011 to Aug 2030 (5 filings). 2 active filings target a date after November 27, 2026.

Transmission owner as filed: BGE (2 filings).

2active projects
410.4active MW
5total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1802 Brandon Shores 230 kV 230 269 Gas Active Aug 2030
AG2-319 Brandon Shores 230 kV 230 150 Battery Withdrawn Dec 2025
C01-2039 Brandon Shores 230 kV 230 141.4 Battery Active Aug 2029
AG2-207 Brandon Shores 230 kV 230 110 Battery Withdrawn Mar 2023
W3-123 Brandon Shores n/r 0 Not reported Withdrawn Jul 2011

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Anne Arundel County, MD

All 29 PJM queue filings in Anne Arundel County, MD.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first