Unionville substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name Unionville as the point of interconnection, all in Orange County, VA.
Target commercial operation dates as filed run from Sep 2016 to Feb 2018 (2 filings).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AB1-067 | Unionville 12.5kV | 12.5 | 0 | Solar | Withdrawn | Sep 2016 |
| AB2-062 | Unionville 115kV | 115 | 0 | Solar | Withdrawn | Feb 2018 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Orange County, VA
- Louisa: 2 active, 203 MW of 5 filed
- Oak Green: 1 active, 150 MW of 3 filed
- Locust Grove-Paytes: 2 active, 40.3 MW of 3 filed
- Somerset: 2 active, 11.8 MW of 14 filed
- Gordonsville: none active of 2 filed
- Lake of the Woods DP-Wilderness DP: none active of 2 filed
- Orange: none active of 2 filed
- Paytes: none active of 2 filed
- South Anna: none active of 2 filed