Substation Scout

Orange, VA interconnection queue

4 active projects totalling 193.3 MW in the PJM queue, plus 19 with terminal status (shown greyed).

4active projects
193.3active MW
23total filed
Queue IDProjectkVMWResourceStatus
AH1-676 Gordonsville 230 kV 230 1,275.9 Gas Withdrawn
C01-2003 Oak Green 230 kV 230 150 Battery Active
AG1-288 Lake of the Woods DP-Wilderness DP 115 kV 115 96.6 Solar Withdrawn
AI2-040 Orange 115kV 115 75 Battery Withdrawn
AG1-502 Oak Green 115 kV 115 64 Hybrid Withdrawn
AG2-608 Unionville - Locust 115 kV 115 64 Hybrid Withdrawn
AG1-289 Lake of the Woods DP-Wilderness DP 115 kV 115 53.4 Battery Withdrawn
AG2-210 Not reported n/r 44.3 Solar Withdrawn
AE1-010 Locust Grove-Paytes 115 kV 115 33 Battery Withdrawn
AG2-609 Unionville - Locust Grove 115 kV 115 32 Hybrid Withdrawn
AC1-076 Pine Glade Solar 115 23.8 Solar In Service
AG2-211 Not reported n/r 20.8 Solar Withdrawn
AH1-123 Locust Grove D.P. 34.5kV 34.5 20 Battery Withdrawn
S97 South Anna Unit 1 230 20 Gas Withdrawn
S98 South Anna Unit 2 230 20 Gas Withdrawn
AE2-134 Pine Glade Solar 115 16.5 Solar In Service
AG1-503 Oak Green 115 kV 115 16 Hybrid Withdrawn
AD1-078 Paytes 115 kV 115 12.6 Solar Withdrawn
AG1-467 Somerset 34.5 kV 34.5 9.4 Solar Withdrawn
AG1-466 Orange 34.5 kV 34.5 8.4 Solar Withdrawn
U4-009 Louisa Gas Turbines Units 1 through 5 230 3 Gas In Service
AB1-067 Unionville 12.5kV 12.5 0 Solar Withdrawn
AB2-062 Unionville 115kV 115 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.