Trowbridge substation interconnection queue
3 active projects totaling 320.7 MW in the PJM queue, plus 2 with terminal status (shown grayed).
5 PJM queue filings name Trowbridge as the point of interconnection, all in Washington County, NC.
Target commercial operation dates as filed run from Sep 2013 to Mar 2028 (5 filings). 3 active filings target a date after November 27, 2026.
3active projects
320.7active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AD1-074 | Macadamia Solar | 230 | 198.8 | Solar | Engineering and Procurement | Mar 2028 |
| AF1-073 | Trowbridge 230 kV | 230 | 120 | Solar | Withdrawn | Oct 2021 |
| AD1-076 | Macadamia Solar | 230 | 72.2 | Solar | Engineering and Procurement | Mar 2028 |
| AD1-075 | Macadamia Solar | 230 | 49.7 | Solar | Engineering and Procurement | Mar 2028 |
| W3-053 | Trowbridge 230kV | 230 | 33.8 | Wind | Withdrawn | Sep 2013 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Washington County, NC
Site Scanner