Mackeys substation interconnection queue

2 active projects totaling 98 MW in the PJM queue, plus 5 with terminal status (shown grayed).

7 PJM queue filings name Mackeys as the point of interconnection, all in NC.

Target commercial operation dates as filed run from Jun 2017 to Dec 2027 (7 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: Dominion (1 filing).

2active projects
98active MW
7total filed
Queue IDProjectkVMWResourceStatusTarget COD
AF1-236 Mackeys 230 kV 230 459.8 Solar Withdrawn Sep 2024
AG1-431 Mackeys 230 kV 230 266.2 Solar Withdrawn Dec 2024
AG1-431A Mackeys 230 kV 230 200 Battery Withdrawn Dec 2024
AB2-189 Mackeys 230kV 230 84 Solar Withdrawn Jun 2017
AA2-178 Ablemarle Beach Solar 230 56 Solar In Service Apr 2021
AE2-034 Albemarle Beach Solar 230 42 Solar Partially in Service - Under Construction Dec 2026
AG2-121 Mackeys 230 kV 230 0 Battery Withdrawn Dec 2027

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Tracked changes at this substation

1 change to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-10-05AG2-121Terminal status0 Active → Withdrawn

Other PJM queue substations in Tyrell County, NC

All 5 PJM queue filings in Tyrell County, NC.

Other PJM queue substations in Washington County, NC

All 21 PJM queue filings in Washington County, NC.