Papermill Tap - Harmony Village substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).

Target commercial operation date as filed: Dec 2032 (2 filings).

Transmission owner as filed: Dominion (2 filings).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1603 Papermill Tap - Harmony Village 230 kV 230 90 Solar Withdrawn Dec 2032
C01-1604 Papermill Tap - Harmony Village 230 kV 230 50 Battery Withdrawn Dec 2032

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Tracked changes at this substation

2 changes to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-09-28C01-1603Terminal status90 Active → Withdrawn
2026-09-28C01-1604Terminal status50 Active → Withdrawn

Other PJM queue substations in Gloucester County, VA

All 15 PJM queue filings in Gloucester County, VA.

Other PJM queue substations in Northampton County, NC

No other substation in Northampton County, NC is named as a point of interconnection in the PJM queue.

All 3 PJM queue filings in Northampton County, NC.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first