Saegers substation interconnection queue

2 active projects totaling 30 MW in the PJM queue, plus 1 with terminal status (shown grayed).

3 PJM queue filings name Saegers as the point of interconnection, all in Lycoming County, PA.

Target commercial operation dates as filed run from Sep 2016 to Dec 2026 (3 filings).

Transmission owner as filed: PPL (1 filing).

2active projects
30active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AF2-140 Patriot Generating Station 230 30 Gas In Service Sep 2024
AH1-707 Saegers 230 kV 230 30 Gas Withdrawn Dec 2026
AA2-008 Patriot Generating Station 230 0 Gas In Service Sep 2016

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Saegers (PPL, 1 mention).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Other PJM queue substations in Lycoming County, PA

All 20 PJM queue filings in Lycoming County, PA.