Substation Scout

Oak Grove-Dahlgren substation interconnection queue

2 active projects totaling 56.3 MW in the PJM queue, plus 1 with terminal status (shown grayed).

3 PJM queue filings name Oak Grove-Dahlgren as the point of interconnection, all in King George County, VA.

Target commercial operation dates as filed run from Dec 2025 to Dec 2029 (3 filings). 2 active filings target a date after November 27, 2026.

2active projects
56.3active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AI2-080 Oak Grove-Dahlgren 230 kV 230 73.4 Solar Withdrawn Dec 2025
AF1-114 Gibson Solar I 230 42 Solar Engineering and Procurement Dec 2028
AF2-091 Gibson Solar I 230 14.3 Solar Engineering and Procurement Dec 2029

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in King George County, VA

All 17 PJM queue filings in King George County, VA.