Birchwood-NUG substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 3 with terminal status (shown grayed).
3 PJM queue filings name Birchwood-NUG as the point of interconnection, all in King George County, VA.
Target commercial operation dates as filed run from Oct 2023 to Jun 2027 (3 filings).
0active projects
0active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AH2-144 | Birchwood-NUG 230kV | 230 | 150 | Battery | Withdrawn | Jun 2027 |
| AH2-145 | Birchwood-NUG 230kV | 230 | 52.3 | Battery | Withdrawn | Jun 2027 |
| AG2-199 | Birchwood-NUG 230 kV | 230 | 35.7 | Solar | Withdrawn | Oct 2023 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in King George County, VA
- Arnold's Corner-Dahlgren: 1 active, 100 MW of 2 filed
- Oak Grove-Dahlgren: 2 active, 56.3 MW of 3 filed
- Arnolds Corner: 1 active, 8.5 MW of 2 filed
- Birchwood: none active of 3 filed