Substation Scout

Manitou-Pleasant Plains substation interconnection queue

1 active project totaling 8.2 MW in the PJM queue, plus 1 with terminal status (shown grayed).

2 PJM queue filings name Manitou-Pleasant Plains as the point of interconnection, all in Ocean County, NJ.

Target commercial operation dates as filed run from Feb 2021 to Apr 2023 (2 filings).

1active projects
8.2active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AI2-212 Manitou-Pleasant Plains 34.5 kV 34.5 10.8 Solar Withdrawn Apr 2023
AE1-142 Toms River Solar 34.5 8.2 Solar In Service Feb 2021

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Ocean County, NJ

All 55 PJM queue filings in Ocean County, NJ.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first