Manitou-Pleasant Plains substation interconnection queue
1 active project totaling 8.2 MW in the PJM queue, plus 1 with terminal status (shown grayed).
2 PJM queue filings name Manitou-Pleasant Plains as the point of interconnection, all in Ocean County, NJ.
Target commercial operation dates as filed run from Feb 2021 to Apr 2023 (2 filings).
1active projects
8.2active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AI2-212 | Manitou-Pleasant Plains 34.5 kV | 34.5 | 10.8 | Solar | Withdrawn | Apr 2023 |
| AE1-142 | Toms River Solar | 34.5 | 8.2 | Solar | In Service | Feb 2021 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Ocean County, NJ
- Lakewood: 4 active, 543 MW of 6 filed
- Oyster Creek: 1 active, 35 MW of 6 filed
- Lakehurst: 1 active, 3 MW of 3 filed
- Larrabee: none active of 11 filed
- Cedar: none active of 8 filed
- Manchester: none active of 2 filed
- Oyster Creek II: none active of 2 filed