Greene-Clark substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).

2 PJM queue filings name Greene-Clark as the point of interconnection, all in OH.

Target commercial operation dates as filed run from May 2019 to Sep 2026 (2 filings).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AD1-140 Kingwood Solar 138 95.8 Solar Withdrawn Sep 2026
AC2-192 Greene-Clark 138kV 138 21 Solar Withdrawn May 2019

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Greene County, OH

All 8 PJM queue filings in Greene County, OH.

Other PJM queue substations in Fayette County, OH

All 16 PJM queue filings in Fayette County, OH.