Greene, OH interconnection queue
1 active project totalling 87.4 MW in the PJM queue, plus 7 with terminal status (shown greyed).
1active projects
87.4active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AD1-140 | Kingwood Solar | 138 | 95.8 | Solar | Withdrawn |
| C01-1073 | chenoweth 345 kV | 345 | 87.4 | Solar | Active |
| AH2-093 | Jasper 69 kV | 69 | 32 | Hybrid | Withdrawn |
| AG1-231 | Glady Run–Xenia 69 kV | 69 | 12 | Solar | Withdrawn |
| AH2-029 | Cedarville 12 kV | 12 | 10.8 | Solar | Withdrawn |
| AB1-095 | Dovetail Biogas Facility | 12 | 0 | Gas | Deactivated |
| AH1-099 | Glady Run–Xenia 69 kV | 69 | 0 | Solar | Withdrawn |
| Z2-019 | Dovetail Biogas Facility | 12.5 | 0 | Gas | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.