Robinson substation interconnection queue
0 active projects totalling 0 MW in the PJM queue, plus 3 with terminal status (shown greyed).
0active projects
0active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AG2-509 | Robinson 69 kV | 69 | 36.3 | Hybrid | Withdrawn |
| AG2-277 | Robinson 69 kV | 69 | 34 | Hybrid | Withdrawn |
| AG2-278 | Robinson 69 kV | 69 | 12 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.