Substation Scout

Fayette, OH interconnection queue

3 active projects totalling 1,956.6 MW in the PJM queue, plus 13 with terminal status (shown greyed).

3active projects
1,956.6active MW
16total filed
Queue IDProjectkVMWResourceStatus
C01-1092 Fayette - Atlanta 345 kV 345 1,425 Gas Active
C01-1180 Fayette 345 kV 345 500 Gas Active
AG2-333 Martinsville - Highland 69 kV 69 38.1 Hybrid Withdrawn
AG2-277 Robinson 69 kV 69 34 Hybrid Withdrawn
AE1-040 Fayette Solar 69 31.6 Solar In Service
AG2-263 Jeffersonville-South Charleston 69 kV 69 31.1 Hybrid Withdrawn
AH2-081 Bentley Farms 69 kV 69 21.3 Solar Withdrawn
AC2-192 Greene-Clark 138kV 138 21 Solar Withdrawn
AH2-082 New Holland - Washington Courthouse 69 kV 69 20 Solar Withdrawn
AI2-053 New Holland 69 kV 69 17.6 Wind Withdrawn
AG2-264 Jeffersonville-South Charleston 69 kV 69 14.7 Hybrid Withdrawn
AG2-265 Jeffersonville-South Charleston 69 kV 69 12 Solar Withdrawn
AG2-278 Robinson 69 kV 69 12 Solar Withdrawn
AH2-007 Texas Eastern - Jeffersonville 69 kV 69 10.1 Other Withdrawn
AI2-250 Greenfield 69 kV 69 10 Solar Withdrawn
AG2-075 Hartland 12.47 kV 12.5 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.