Curdsville-Willis Mtn substation interconnection queue

1 active project totaling 60 MW in the PJM queue, plus 1 with terminal status (shown grayed).

2 PJM queue filings name Curdsville-Willis Mtn as the point of interconnection, all in Buckingham County, VA.

Target commercial operation dates as filed run from Dec 2025 to Dec 2026 (2 filings). 1 active filing targets a date after November 27, 2026.

1active projects
60active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE2-259 Blue Rock Solar 115 60 Solar Engineering and Procurement Dec 2026
AI2-448 Curdsville-Willis Mtn 115 kV 115 36.8 Solar Withdrawn Dec 2025

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Buckingham County, VA

All 27 PJM queue filings in Buckingham County, VA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first