BYRON - WEMPLETOW substation interconnection queue
2 active projects totaling 463.6 MW in the PJM queue.
2 PJM queue filings name BYRON - WEMPLETOW as the point of interconnection, all in Ogle County, IL.
Target commercial operation dates as filed run from Jun 2030 to Jul 2030 (2 filings). 2 active filings target a date after November 27, 2026.
Transmission owner as filed: ComEd (2 filings).
2active projects
463.6active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| C01-1234 | BYRON - WEMPLETOW 345 kV | 345 | 288.6 | Solar | Active | Jun 2030 |
| C01-1235 | BYRON - WEMPLETOW 345 kV | 345 | 175 | Battery | Active | Jul 2030 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Ogle County, IL
- Byron - Wayne: 1 active, 198.6 MW of 3 filed
- Byron: 1 active, 43 MW of 3 filed
- Rochelle: 3 active, 22 MW of 3 filed
- Twombley Road: 1 active, 20 MW of 2 filed
- Twombly Road: 1 active, 15.4 MW of 2 filed
- Stillman Valley: none active of 4 filed
- Maryland: none active of 3 filed
- White Rock - Wayne: none active of 3 filed
- Dixon-Cherry Valley: none active of 2 filed
- Lancaster-Maryland: none active of 2 filed