Substation Scout

Brandon Shores 230 kV

PJM queue ID C01-2039

Brandon Shores 230 kV (C01-2039) is listed in the PJM interconnection queue as a 141.4 MW battery project in Anne Arundel County, MD. The filing names Brandon Shores as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of August 31, 2029.

Queue IDC01-2039
Project nameBrandon Shores 230 kV
Status (as published)Active
SubstationBrandon Shores
Point of interconnectionBrandon Shores 230 kV
CountyAnne Arundel
StateMD
Voltage230 kV
Capacity141.4 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-08-31
Source datasetcycle

Same substation and county

Brandon Shores substation: 5 requests in the PJM queue, 2 active totaling 410.4 MW.

Queue IDProjectMWResourceStatus
C01-1802Brandon Shores 230 kV269GasActive
AG2-319Brandon Shores 230 kV150BatteryWithdrawn
AG2-207Brandon Shores 230 kV110BatteryWithdrawn
W3-123Brandon Shores0Not reportedWithdrawn

Anne Arundel, MD: 29 requests in the PJM queue, 11 active totaling 1,322.7 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperFS CT Project LLC
Transmission ownerBGE
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy300.0
MW capacity141.4
MFO600.0
Submitted date4/25/2026
Last updated6/8/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first