TNMP FM524 Substation substation interconnection queue

2 active projects totalling 622 MW in the ERCOT queue.

2active projects
622active MW
2total filed
Queue IDProjectkVMWResourceStatus
27INR0095 Bulldog Power (TEF - Due Diligence) 138 311 Gas SS Completed, FIS Completed, No IA
30INR0073 Bulldog Power II 138 311 Gas SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.